Pave Your Way resurfacing specialists
  • Call: 01531 633 672

This work is the second part of a luxurious four house development in Hanley castle Worcestershire. We had previously connected the site to the mains sewer and mains water supply. This next phase involved putting in the entrance road and extending the mains sewer and water connections on to the site. First the road way was excavated to the approximately dimensions of the drawings,with the topsoil stored on site for future use in the project. Next a capping layer of crushed concrete is brought in and compacted to provide the initial base to the roadway. Once all utilities and drainage have been completed ,further layers of sub base will be added to a finished level prior to the finished surface. Also completed were the sewer and water pipes brought on to site . The next phase will be the footings and drainage .